Before building works start in Singapore, the plans have to be approved under the Building Control Act. A BCA BP submission is the application through which a project’s Qualified Person submits the building plans, showing the layout, construction and safety provisions of the proposed works, so that the Building and Construction Authority can check them against the Building Control Regulations. It sits alongside the structural plan (ST) submission and, for most new developments, follows planning permission from URA.
This guide walks through the process step by step: what the building plans are, who submits them, how they relate to structural plans and other approvals, and where projects tend to lose time. It is written from a practising structural engineer’s perspective for owners and developers who want to understand the sequence, not for professionals completing the forms.
Step 1: Understand where BP fits
Building approval in Singapore is layered. It helps to separate three questions that are answered by different submissions.
- Planning permission from URA answers whether the proposed use, density, height and form are acceptable on that site under the Master Plan and development control guidelines.
- Building plan (BP) approval from BCA answers whether the building’s layout and construction comply with the Building Control Regulations, covering matters such as means of access, accessibility, safety barriers, ventilation and lighting, and other prescribed requirements.
- Structural plan (ST) approval from BCA answers whether the structure is adequately designed to carry its loads safely.
Other agencies run their own approvals in parallel, most importantly SCDF for fire safety, along with PUB, NEA, LTA and others where relevant. A project is ready to build only when the necessary approvals are in hand and the permit to commence structural works has been issued. Our guide to structural plan submission in Singapore covers the ST side in detail.
Step 2: Appoint the right Qualified Persons
The Building Control Act requires plans to be prepared and submitted by a Qualified Person, meaning a registered architect or Professional Engineer with a valid practising certificate. For building plans, the QP is usually the architect, though the regulations allow a Professional Engineer in the civil or structural discipline to act as QP for building plans in certain cases. Structural plans must be prepared by a Professional Engineer in the civil or structural discipline.
Appointing the QPs early matters because the building plans and the structural plans must describe the same building. The architect’s layout determines where columns, walls and transfer structures can go; the structural engineer’s constraints determine what spans and openings are realistic. Our article on what a structural engineer does explains why that early dialogue saves time.
Step 3: Prepare the building plans
The building plans describe the proposed works in sufficient detail for compliance to be checked. They typically include site and location plans, floor plans, sections and elevations, and details of the elements regulated under the Building Control Regulations. Depending on the project, supporting documents may cover accessibility, buildability, environmental sustainability, household or storey shelters, and other requirements.
Two of these supporting areas deserve particular mention because they affect design decisions early.
Buildability
Projects within the scope of the buildability framework must achieve minimum buildable design and constructability scores. The score reflects choices about structural systems, standardisation and prefabrication, so it is not something that can be fixed at the last minute. Our explainer on the buildability score in Singapore covers how it works.
Sustainability and shelters
Larger new buildings and major alteration works may need to meet environmental sustainability requirements, with declarations submitted alongside the building plans. Residential developments may require household or storey shelters, which have their own submission and approval process and strong structural implications, since shelter walls and slabs are designed to particular standards.
Step 4: Make the BCA BP submission
Submissions are made electronically through the government’s CORENET platform. Singapore is in the middle of a transition to CORENET X, which replaces separate submissions to each agency with a coordinated process organised into gateways: a Design Gateway, an optional Piling Gateway, a Construction Gateway and a Completion Gateway. In the gateway process, the project’s QPs submit a coordinated model and supporting documents, and the participating agencies review them together.
Under the implementation plan announced by URA and BCA, CORENET X submissions are mandatory for larger new projects above a gross floor area threshold, while smaller projects can continue to use the existing CORENET route for now. The thresholds and dates have been revised more than once, so your QP should confirm which route applies to your project at the time of submission.
Whichever route applies, the submission is endorsed by the relevant QPs, and fees are payable according to the prevailing schedule. Incomplete submissions are the single largest source of avoidable delay, so the coordinating QP should check that every required document and declaration is in place before lodging.
Step 5: Respond to queries and obtain approval
BCA and the other agencies review the submission and may raise queries or require amendments. The QP responds with clarifications or revised plans. When the building plans satisfy the requirements, approval is granted, sometimes with conditions that must be met during construction or before completion.
Approval of the building plans does not by itself authorise construction to start. For structural works, the ST plans must also be approved and a permit to carry out structural works obtained, with a builder appointed and site supervision arrangements in place. Only then can work begin on site.
Amendments during construction
Designs evolve. When changes are made after approval, the QP must assess whether they require an amendment submission. Changes that affect regulated matters, such as layouts, exits or structural elements, generally do. Building something different from the approved plans without an amendment creates problems that surface at completion, when the QP must certify that the works comply with the approved plans before the Temporary Occupation Permit can be issued.
Where BP submissions commonly go wrong
Most delays are not caused by the authorities. In our experience they come from a familiar set of issues.
- Uncoordinated plans. Architectural and structural drawings that do not match, or services that clash with structure, generate queries and resubmissions.
- Unsettled design. Submitting before the client has finalised the scheme leads to repeated amendments.
- Late compliance thinking. Buildability, accessibility and fire safety requirements addressed only at submission force redesign.
- Missing supporting documents. Declarations, scores and agency clearances left until the end hold up the whole package.
For owners of existing buildings, the same discipline applies to alteration works. Our guide to A&A works in Singapore explains when alterations need building plan approval and when they can be treated as minor or exempt.
What owners can do to help
An owner does not prepare the submission, but they influence its speed. Settle the brief early, give the design team complete information about the site and existing conditions, make decisions promptly when queries arise and resist late changes. Budget realistic time for approvals in the programme rather than assuming they will be instant.
Most importantly, make sure the architect and structural engineer are working together from the start. If you would like an early structural view on a scheme before it goes in for approval, our structural engineering consultancy can review the design and flag issues while they are still cheap to fix.
Frequently asked questions
What is a BCA BP submission?
It is the application in which a project’s Qualified Person submits building plans to BCA so that the proposed works can be checked against the Building Control Regulations. It is separate from the structural plan submission and from URA planning permission, though the three must describe the same building.
Who can submit building plans to BCA?
Building plans must be submitted by a Qualified Person, which means a registered architect or Professional Engineer with a valid practising certificate, appointed by the owner or developer for the appropriate type of work.
What is the difference between BP and ST plans?
Building plans cover the layout and regulated building matters such as access, safety barriers, ventilation and accessibility. Structural plans, prepared by a civil or structural Professional Engineer, cover the design of the foundations and structural frame and how the building carries its loads.
Can construction start once the building plans are approved?
Not by itself. Structural plans must also be approved and a permit to carry out structural works obtained, with a builder and site supervision in place, before structural works can begin on site.
Is CORENET X compulsory for building plan submissions?
CORENET X is being phased in. It is mandatory for new projects above a gross floor area threshold set by URA and BCA, while smaller projects can currently continue on the existing CORENET route. Your QP should confirm the current requirement before submission.
How long does BCA take to approve building plans?
A complete, well-coordinated building plan submission can be processed by BCA within a few weeks, but the overall approval period depends heavily on how many rounds of queries and amendments are needed. Parallel clearances from SCDF and other agencies also affect the timeline. Owners should allow several months in the programme from first submission to approvals for a new building, and confirm current processing standards with their QP.
How much does a BCA building plan submission cost?
BCA charges plan fees according to its prevailing fee schedule, generally based on the floor area of the proposed works, with separate fees for structural plans. The larger cost for most owners is the professional fees of the architect and engineers who prepare and endorse the plans, which vary with the size and complexity of the project. Ask your QP for an itemised estimate of both authority and professional fees.
Do I need BCA building plan approval to renovate my house?
Not always. Minor internal renovations, such as new finishes and non-structural fittings, are generally exempt, but additions and alterations that change the building’s layout, structure, means of escape or floor area usually need approval. Extensions, new floors, removal of structural walls and roof changes typically require building and structural plans from a Qualified Person. Check current BCA requirements before starting, since the threshold depends on the specific works.
What happens if building works are carried out without BCA approval?
Carrying out building works that need approval without it is an offence under the Building Control Act and can lead to fines, stop-work orders and orders to remove or regularise the works. Unauthorised works also cause problems later, for example at the Temporary Occupation Permit stage, during a sale or when seeking insurance. Regularising them usually means engaging a QP to assess, document and, where necessary, strengthen what has been built.
Related reading
- Cracks in Walls and Ceilings: When to Call an Engineer
- Fire Safety Certificate (FSC) in Singapore Explained
- PEB Singapore: How to Verify a Professional Engineer
- Qualified Person Singapore: QPs and Accredited Checkers
Preparing a building plan submission and want the structural side coordinated from the outset? Talk to our consultancy or get in touch.